People

Agenda

  • Discuss and decide goals for this iteration.

Notes

  • This iteration is about actually doing concurrent building.

Current projects

  • N/A

Tasks for this week

Tasks may be part of a project or be random small ones (max an hour) that just need doing.

what Who estimate(h)
Try concurrent building with two workers Lars 4h
Total liw

Task descriptions

  • Try concurrent building with two workers: Set up an ick cluster with at least two workers and at least two projects. Trigger both projects. Do both build at the same time? Do both build correctly?

    Acceptance criteria: Manual testing shows things work OK. Any issues either get fixed or reported.